department of state
Public Service Commission
IN THE MATTER OF THE |
ADOPTION OF RULES AND |
PROCEDURES TO IMPLEMENT |
THE RENEWABLE ENERGY |
PORTFOLIO STANDARDS | PSC
ACT, 26 DEL. C. §§351-363, AS | REGULATION
AS APPLIED TO RETAIL | DOCKET NO. 56
ELECTRICITY SUPPLIERS |
(OPENED AUGUST 23, 2005) |
ORDER NO. 6697
general notice
Adoption of Rules and Procedures to Implement the Renewable Energy Portfolio Standards
This 23rd day of August, 2005, the Commission determines and Orders the following:
1. In July, the General Assembly and Governor enacted the Renewable Energy Portfolio Standards Act (“the Act”), 75 Del. Laws ch. 205 (July 12, 2005), codified in main part at 26 Del.C. §§351-363. The Act directs each retail supplier of electricity in this State to demonstrate, each year, that it has accumulated a specified level of “renewable energy credits.” “Renewable energy credits” are tradable instruments representing electricity derived from “eligible energy sources” or “customer-owned generation.” The requirement level of such credits is keyed to a percentage of the supplier’s overall adjusted retail load and the percentage increases each year. The Act gives this Commission the duty to implement and enforce the new renewable energy portfolio standards in the case of non-municipal “retail electricity suppliers.1 The Act charges the Commission to complete its start-up tasks and have its implementing regulations in place by July 31, 2006.2
2. The Commission now opens this docket to begin to consider its assigned obligations in implementing the Act. The list of things to be done appears to be long; running from determining what can be certified as an “eligible energy resource,” to how, and by whom, “renewable energy credits” are to be tracked. Given the tasks, and given that Staff has identified some questions that might need further exploration or clarification, the Commission is not yet in a position to propose the text for its implementing regulations. Rather, by this Order, the Commission adopts a broad procedural flight path to make sure the Commission’s regulations arrive before July 31, 2006. Thus, initially, the Commission sets aside two months for the Staff to conduct informal, but public, workshops in order to better educate Staff. At those workshops, Staff can obtain interested persons’ views on the meaning of some parts of the statutory text and also listen to possible scenarios for how the various requirements of the Act can be efficiently implemented. After such workshops, Staff can prepare proposed rules, or other needed documents, for the Commission’s review. The Commission would hope to have such drafts by November 10, 2005. If the Commission accepts Staff’s drafts, the proposed regulations will then be subject to scrutiny and comment under the rule-making process dictated by the Administrative Procedures Act.3
3. So far, Staff, and counsel, have identified some instances in the Act where, in their reading, the text allows for various interpretations. Consequently, the Commission specifically invites those persons or entities who had a hand in the drafting of the Act to participate in Staff’s initial workshops. While drafters’ intent cannot change enacted text, an appreciation of the background for specific language can aid Staff’s ability to get a clear view of textual meaning.
4. Also, under the Act’s regime, the State Energy Office and the Controller General are given the duty to supervise compliance by municipal electric power entities (who have not chosen the “opt-out” alternative).4 The Commission believes it would be beneficial for those other offices and this Commission to act under a shared understanding of the Act’s requirements. Consequently, the Commission extends to those offices an invitation to participate both in the informal workshops and the later rule-adoption proceedings.5
Now, therefore, IT IS ORDERED:
1. That this docket is instituted to adopt rules and regulations and other directives needed to implement the Renewable Energy Portfolio Standards Act, 75 Del. Laws ch. 205 (July 12, 2005), codified in main part at 26 Del.C. §§351-363, and to govern the Commission’s responsibilities under such enactment provisions.
2. That, as an initial step in the process, the Commission Staff shall conduct public informal workshops to better educate the Commission about the terms of the Renewable Energy Portfolio Standards Act and such statute’s requirements. The number, timing, place, and agendas for such workshops shall be set by Staff. Staff shall endeavor to have a wide range of interested persons participate.
3. That, after conducting such workshops, Staff shall present to the Commission a draft of a proposed set of implementing rules or regulations as well as recommendations for any other action by the Commission. Staff shall endeavor to file its draft rules and recommendations by November 10, 2005.
4. That the Secretary shall initiate a service list for participants in the informal workshops conducted under Ordering paragraph 2. Persons or entities choosing to be included on the service list will receive notice of the workshop and documents considered at those workshops. Staff shall, if necessary or appropriate, provide public notice of the informal workshops.
5. That the Secretary shall publish in the manner described below the notice attached as Exhibit “A”. Such notice shall be published in The News Journal newspaper on or before September 1, 2005. The notice shall also be sent to the Delaware Registrar of Regulations for publication in the notice section of the Delaware Register of Regulations.
6. That the Secretary shall send by United States mail a copy of this Order with exhibit to:
(a) the Division of the Public Advocate;
(b) the State Energy Coordinator of the State Energy Office;
(c) the Controller General of Delaware;
(d) PJM-Environmental Services, Inc.; and
(e) the Secretary, Department of Natural Resources and Environmental Control.
7. After receipt of the documents described in Ordering paragraph 3, the Commission will enter such further Orders as may be appropriate.
8. That the Commission reserves the jurisdiction and authority to enter such further Orders in this matter as may be deemed necessary or proper.
BY ORDER OF THE COMMISSION:
E X H I B I T “A”
NOTICE OF INITIATION OF DOCKET AND PROCEEDINGS TO IMPLEMENT THE RENEWABLE ENERGY PORTFOLIO STANDARDS ACT
TO: ALL CONSUMERS, RETAIL ELECTRIC
SUPPLIERS, GENERATORS, AND OTHER
INTERESTED PERSONS
In 2005, the General Assembly and Governor enacted the Renewable Energy Portfolio Standards Act (“the Act”), 75 Del. Laws ch. 205 (July 12, 2005). The Act will require all entities selling electric supply in Delaware to meet, in each compliance year, certain minimum thresholds for “renewable energy credits.” The credits are linked to electricity produced by “eligible energy resources” and by “customer-owned generation.”
The Public Service Commission (“PSC) has initiated this docket to develop regulations and other directives to implement this new Act for “retail electric suppliers.” As an initial step in that process, the PSC Staff will conduct a series of informal public workshops to educate Staff about the requirements of the Act, the PSC’s duties in both implementing the renewable credit regime and supervising future compliance, and the availability of the PJM-EIS GATS system to assist in monitoring compliance. After the workshops, the PSC Staff will propose draft regulations that will be considered by the PSC and then proposed for adoption under the rule-making procedures of the Delaware Administrative Procedures Act.
If you wish to be given notice of these workshops, you must file to be included on the PSC’s initial service list in this docket. To be listed, you must deliver a letter to the address set out below. You must include your name, organization (if any), address, voice and facsimile telephone numbers, and Internet e-mail address. Such letter should be delivered to:
Delaware Public Service Commission
861 Silver Lake Boulevard
Cannon Building, Suite 100
Dover, DE 19904
Attn: PSC Reg. Dckt. No. 56
You should try to deliver that letter by September 12, 2005. You can read PSC Order No. 6697 (Aug. 23, 2005) (available at www.state.de.us/delpsc) to gain more information about the initial stage of this matter. You can also direct inquiries to David Bloom at either 1-800-282-8574 (Delaware only) or (302) 739-4247 (text telephone also) or by Internet e-mail addressed to david.bloom@state.de.us. The public is particularly invited to participate in this docket.
4 See 26 Del.C. §358(c).
7 See 26 Del.C. §359(a), (c)-(d).
8 See 26 Del.C. §359(d).