Delaware.gov logo

Authenticated PDF Version

DEPARTMENT OF NATURAL RESOURCES AND ENVIRONMENTAL CONTROL

Division of Watershed Stewardship

Shoreline and Waterway Management Section

Statutory Authority: 7 Delaware Code, Section 6803(c) (7 Del.C. §6803(c))
7 DE Admin. Code 5102

FINAL

Secretary’s Order No.: 2016-WS-0023

5102 Regulation Governing Beach Protection and the Use of Beaches

Date of Issuance: July 15, 2016

Effective Date of the Amendment: August 11, 2016

Under the authority vested in the Secretary of the Department of Natural Resources and Environmental Control (“Department” or “DNREC”) pursuant to 7 Del.C. §§6006, 6010, and other relevant authority, the following findings of fact based on the record, reasons and conclusions are entered as an Order of the Secretary in the above-referenced regulatory proceeding.

The revised regulatory amendments that will be adopted through this Order represent the culmination of many years of work and extensive public outreach by the Department, which includes (but is certainly not limited to) multiple discussions with stakeholders, legislators, and, of course, the public in general. These revised regulatory amendments are responsive to the concerns that have been raised in said discussions and through the Department’s regulatory development process which has taken place over the course of the last few years.

Background, Procedural History and Findings of Fact

This Order relates to the proposed revised regulatory amendments to 7 DE Admin. Code 5102: Regulation Governing Beach Protection and the Use of Beaches (“regulatory amendments”, “Amendments”). The purpose of this action is to (1) incorporate legislative changes to Delaware’s Beach Preservation Act (7 Del.C. Ch. 68); (2) incorporate Division policies and construction standards that will result in less damage to structures and more protection of the dune and beach resources; and (3) provide consistency and additional clarity by harmonizing various provisions of the aforementioned existing Regulation.

Delaware’s Beach Preservation Act was passed in 1972 as the General Assembly recognized that Delaware’s beaches were rapidly deteriorating due to a combination of natural processes and continuing encroachment. The Department was charged through this act to enhance, preserve and protect the public and private beaches of the state and to mitigate beach erosion and minimize storm damage.

A significant amendment to the Act was passed by the General Assembly in 1996 which required the Department to take additional steps to minimize the impacts on the beach and dunes from any construction that took place seaward of the building line. The legislation, among other things, amended 7 Del.C. Ch. 68, by adding a new sentence at the end of subsection 6805(d) that reads as follows:

If any structure proposed to be built in whole or in part seaward of the building line could reasonably be reduced in size or otherwise altered in order to eliminate or diminish the amount of encroachment over the building line, the Department shall require such reduction or alternation as a condition of granting the permit or letter of approval.

The methodology by which to achieve the objective stated in the legislation was developed by the Department as a set of procedures and guidance that became known as “The Four Step Process.” This guidance has not, until now, been incorporated into the Beach Regulations. By incorporating the Four Step Process into the regulation, as it has existed and been applied during the past 20 years, assures consistency, transparency and certainty for the public.

Pursuant to 7 Del.C. §6803(c), the Department’s Division of Watershed Stewardship (“Division of WSS”, “WSS”), Shoreline and Waterway Management Section (“SWMS”), is charged with promulgating rules and regulations to effectuate the purpose of the Beach Preservation Act (“Act”), which is to enhance, preserve and protect the public and private beaches throughout the State of Delaware. The Department’s Division of WSS, SWMS, commenced the regulatory development process with Start Action Notice 2014-05, dated May 20, 2014. The Department published its initial proposed regulatory amendments in the October 1, 2015 Delaware Register of Regulations.

After six (6) public workshops, eleven (11) Regulatory Advisory Committee meetings (all of which were open to the public), and various other meetings, discussions and reviews, the Department placed legal notices in both the News Journal and the Delaware State News, advertising that a public hearing would be held on November 7, 2015 to provide an opportunity for the public to comment on these proposed regulatory amendments. Members of the public attended that hearing, and many provided comment to the Department regarding the same, both at the time of the hearing and during the post-hearing phase of this regulatory promulgation. After extending the public comment period an additional fifteen (15) days (in order to provide people a greater opportunity to participate in this process), the formal hearing record closed with regard to public comment on December 7, 2015.

Subsequent to the aforementioned record closing, the Department’s Division of WSS, SWMS, then began a thorough review of the formal hearing record generated to date with respect to this proposed promulgation, including, but not limited to, a detailed review of the formal hearing transcript, and all comment received from the public. The Division of WSS, SWMS, then prepared its formal Technical Response Memorandum (“TRM”), dated January 29, 2016, which documents the exhaustive review performed by the Department with regard to this proposed regulatory promulgation, and offers the Department’s response to all comments received throughout this long regulatory process.

It should be noted that the largest number of comments received by the Department in this matter was related to the issue of whether the proposed regulations represented any taking of private property. The regulations are not a taking as they allow an existing property owner to rebuild or repair structures, even on lots that are traversed by the building line established by law, as long as they work within the existing footprint and minimize encroachment. The Four Step Process, now included in the regulations, ensures that structures do not protrude excessively seaward in comparison to their adjacent neighbors. The regulation of the use of property for the benefit of the public and the protection of natural resources, such as through zoning, has been routinely upheld by the courts as a legitimate exercise of authority. Since 1972, no Delaware Court has found that the Delaware Regulations for beach preservation constitute an unconstitutional taking.

Of note is the fact that, in response to the numerous meritorious comments and suggestions received, the Department has proposed only one change to the initially proposed regulatory amendments, to wit: the clerical correction of an erroneous definition of “National American Vertical Datum” (“NAVD”), as follows:

National Geodetic [North] American Vertical Datum (NGAVD)”

Due to the fact that this revision does not alter the meaning or function of the proposed regulatory amendments, it is not construed to be substantive in nature. Therefore, according to 29 Del.C. §10118(c), no additional re-publication or re-noticing of these proposed Amendments is necessary at this time.

As set forth in the Department’s TRM referenced above, the Department has the statutory basis and legal authority, pursuant to 7 Del.C. §6803(c), to promulgate rules and regulations to effectuate the purpose of the Beach Preservation Act. It should also be noted that all proper notification and noticing requirements concerning this matter were met by the Department. Proper notice of the hearing was provided as required by law.

Subsequent to receiving the Division of WSS, SWMS’s aforementioned TRM, the Department’s presiding hearing officer, Lisa A. Vest, then prepared a Hearing Officer’s Report dated May 6, 2016 (“Report”). The Report documents the proper completion of the required regulatory development process, establishes the record, and recommends the adoption of the proposed revised regulatory amendments, as attached to the Report as Appendix “B”.

Reasons and Conclusions

Based on the record developed by the Department’s experts and established by the Hearing Officer’s Report, I find that the proposed revised regulatory amendments, to wit: 7 DE Admin. Code 5102: Regulation Governing Beach Protection and the Use of Beaches, are well-supported. Therefore, the recommendations of the Hearing Officer are hereby adopted, and I direct that the proposed regulatory revised regulatory amendments be promulgated as final.

I find that the Department’s experts in the Division of WSS, SWMS, fully developed the record to support adoption of these revised regulatory amendments. The adoption of these revised regulatory amendments will allow Delaware to (1) incorporate legislative changes to the Beach Preservation Act (7 Del.C. Ch. 68); (2) incorporate Division policies and construction standards that will result in less damage to structures and more protection of the dune and beach resources; and (3) provide consistency and additional clarity by harmonizing various provisions of the aforementioned existing Regulation.

In conclusion, the following reasons and conclusions are entered:

1. The Department has the statutory basis and legal authority to act with regard to the proposed revised amendments to 7 DE Admin. Code 5102: Regulation Governing Beach Protection and the Use of Beaches, pursuant to 7 Del.C. §6803(c);

2. The Department has jurisdiction under its statutory authority, pursuant to 7 Del.C. Ch. 60, to issue an Order adopting the proposed revised regulatory amendments as final;

3. The Department provided adequate public notice of the initial proposed regulatory amendments and all proceedings in a manner required by the law and regulations, provided the public with an adequate opportunity to comment on said regulatory amendments, including at the time of the public hearing held on November 7, 2015, and held the record open through close of business on December 7, 2015, as referenced in detail above, consistent with 29 Del.C. §10118(a), in order to consider all public comment on the same before making any final decision;

4. While the Department made a clerical revision to the initial proposed regulatory language correcting a definition, as set forth in the above-referenced TRM of January 29, 2016, such change does not alter the meaning or function of the proposed regulatory amendments, is not substantive, and therefore, according to 29 Del.C. §10118(c), no additional re-publication or noticing of the same is necessitated at this time;

5. The Department’s Hearing Officer’s Report, including its established record and the recommended proposed revised regulation amendments, as set forth in its Appendix “B”, are hereby adopted to provide additional reasons and findings for this Order;

6. Promulgation of the proposed revised regulatory amendments to 7 DE Admin. Code 5102: Regulation Governing Beach Protection and the Use of Beaches, will allow Delaware to (1) incorporate legislative changes to the Beach Preservation Act (7 Del.C., Ch. 68); (2) incorporate Division policies and construction standards that will result in less damages to structures and protections of the dune and beach resources; and (3) provide consistency and additional clarity by harmonizing various provisions of the aforementioned existing Regulation;

7. The Department has reviewed these proposed revised regulatory amendments in the light of the Regulatory Flexibility Act, consistent with 29 Del.C. Ch. 104 (version applicable to all regulations initially published on or before December 31, 2015), and believes the same to be lawful, feasible and desirable, and that the recommendations as proposed should be applicable to all Delaware citizens equally;

8. The Department’s proposed revised regulatory amendments, as published in the October 1, 2015 Delaware Register of Regulations, and as revised and set forth in Appendix “B” of the aforementioned Hearing Officer’s Report, are adequately supported, are not arbitrary or capricious, and are consistent with the applicable laws and regulations. Consequently, they are approved as final revised regulatory amendments, which shall go into effect ten days after its publication in the next available issue of the Delaware Register of Regulations; and

9. The Department shall submit this Order approving as final the proposed revised regulatory amendments to 7 DE Admin. Code 5102: Regulation Governing Beach Protection and the Use of Beaches, to the Delaware Register of Regulations for publication in its next available issue, and provide such other notice as the law and regulation require and the Department determines is appropriate.

David S. Small, Secretary

5102 Regulation Governing Beach Protection and the Use of Beaches

1.0 Definitions

1.1 As used in these Regulations, tThe following words and terms, when used in this regulation, shall have the following meanings indicated below, unless the context clearly indicates otherwise:

Accidental Event” means a sudden, unintended, and unexpected occurrence that results in damage or loss of property

“Act” means the Beach Preservation Act of 1972, (Title 7, Del.C. Ch. 68).

Act of God” means a sudden and inevitable occurrence caused by natural forces and not by the agency of man, such as a flood, earthquake, or a similar catastrophe.

“Beach” means that portion of the shore of any body of water which extends from the mean high water mark inland one thousand feet, or to a roadway for automobiles, whichever is closer means that area from the Delaware/Maryland line at Fenwick Island to the Old Marina Canal immediately north of Pickering Beach, which extends from the mean high water line of the Atlantic Ocean and Delaware Bay landward 1,000 feet and seaward 2,500 feet, respectively.

Beach Access Facility Structure means any structure, improvement or facility constructed, installed or maintained for the primary purpose of obtaining or facilitating access to and from the berm and foreshore of the beach over, on or across the primary coastal dune.

Beach Enhancement means the process of improving or increasing the recreational and/or storm protection value of a beach.

Beach Erosion” means the wearing away of a beach by water or the elements.

Beach Nourishment” means the process of replenishing a beach with material (usually sand) obtained from another location.

Beach Preservation means the process of maintaining the recreational and/or storm protection value of a beach means the protection and control of the beach by the conduct and regulation of work and activities likely to affect the physical condition of the beach or shore, and includes, but is not limited to, erosion control, hurricane protection, coastal flood control, shoreline and offshore rehabilitation.

Beach Protection means the process of preventing the decrease of recreational and/or storm protection values of a beach.

Berm means the nearly horizontal part of the beach between the foreshore and primary dune formed by the deposit of material by wave action.

Breakwater means a marine structure constructed to protect a shore area, harbor, anchorage, or basin from the undesirable effects of wave action.

Buildable Lot” means a lot upon which construction of a structure is permissible by all State, Federal, and local codes and regulations.

Building means any roofed and walled structure built for permanent or semi-permanent use.

Building Line means the line generally paralleling the coast, set forth on maps prepared by the Division with reference to the National Geodetic Vertical Datum (NGVD) and the Delaware State Plane Coordinate System, and based upon information provided by topographic survey means a line generally paralleling the coast, seaward of which construction of any kind shall be prohibited without a permit or letter of approval from the Department. The Building Line shall be set forth on maps prepared by the Department with reference to a vertical datum commonly used by land surveyors, the Delaware State Plane Coordinate System and topographical surveys. The Building Line is located as follows:

a. Along beaches extending from the Delaware/Maryland line to the tip of Cape Henlopen - 100 feet landward of the adjusted seawardmost 10 9-foot elevation contour above NGVD NAVD;

b. Along beaches extending from the tip of Cape Henlopen to the southernmost limit of Rosemary Street in Primehook Prime Hook Beach - 100 feet landward of the adjusted seawardmost 7 6-foot elevation contour above NGVD NAVD;

c. Along beaches extending from the southernmost limit of Rosemary Street in Primehook Prime Hook Beach to the Old Marina Canal north of Pickering Beach - 75 feet landward of the adjusted seawardmost 7 6-foot elevation contour above NGVD NAVD;

d. oOr at the landward limits of the Beach, as defined in these Regulations, whichever is most seaward.

Within the corporate limits of Rehoboth Beach and Bethany Beach, in commercial areas containing boardwalks and where no natural dune exists, the Building Line shall be along the westerly edge of the boardwalk.

Bulkhead means an upright structure or partition built parallel or nearly parallel to the shoreline, primarily to retain or prevent land from sliding and secondarily, to protect upland from beach erosion and damage from wave action. A bulkhead is generally of lighter construction than a seawall.

Coastal Engineering Standards of Storm Protection” means level of protection for a location that consists of at least 100 feet of vegetated dune landward of the seawardmost 9-foot elevation contour above NAVD from the Delaware/Maryland line to the tip of Cape Henlopen, 100 feet landward of the seawardmost 6-foot elevation contour above NAVD from the tip of Cape Henlopen to Rosemary Street in Prime Hook Beach, and 75 feet landward of the seawardmost 6-foot elevation contour above NAVD from Rosemary Street in Prime hook Beach to the Old Marina Canal north of Pickering Beach.

Complete Destruction means the damage or destruction of any structure by any means whatsoever to the extent that, in the judgment of the Division, 75% or more of the original structure, or if a building, more than 50% of the original foundation pilings, are unsuitable for incorporation into reconstruction of the structure.

“Construction” means any work or activity which is likely to have a substantial physical effect on existing coastal conditions or natural shore processes. Construction as used in these Regulations shall also include reconstruction, restoration, repair, alteration and placement if said terms are not otherwise included for clarification a material physical effect on existing coastal conditions or natural shore and inlet processes.

Deck” means an open platform extending from a house or other building.

Department means the Department of Natural Resources and Environmental Control.

Dike means a wall or mound built around a low lying area to prevent flooding.

Division means the Division duly authorized by the Secretary as responsible for administering these Regulations.

Dune means a mound, hill or ridge of windblown sand, either bare or covered with vegetation, naturally or artificially accumulated.

Dune Zone means that area lying between the Building Line and elevation contours, which are used as a basis for determining the location of the Building Line. (See Building Line definition.)

Emergency means the existence of beach conditions unreasonably dangerous to persons or property any unusual incident which endangers the health safety or resources of the general public, including damages or erosion of any shoreline resulting from a hurricane, storm or any such natural disturbance.

Excavation means the process of digging out material.

Expansion means the enlargement of a structure.

Filling means the process of depositing or placing material to raise the level of a certain area.

Foreshore means the part of the shore lying between the crest of the seaward berm (or upper limit of wave action at high tide) and the ordinary low water mark, that is ordinarily traversed by the uprush and backrush of the waves as the tides rise and fall.

Geology means the relationship of the earth and the materials of which it is composed, to the changes which it has undergone, is undergoing, or is likely to undergo.

Geomorphology means the form and general configuration of the earth's surface and the changes that take place in the evolution of land forms.

Groin means a shore protection structure built (usually perpendicular to the shoreline) to trap littoral drift or retard erosion of the shore.

Hydraulics means the effects of water or other fluids in motion.

Improve” means to change an existing structure in order to enhance its integrity or value.

Jetty means a structure extending into a body of water, and designed to prevent shoaling of a channel by littoral materials, and to direct and confine the stream or tidal flow.

Littoral” means pertaining to the shore of a sea.

Littoral Current means a longshore current generated by waves breaking at an acute angle to the shoreline, and which moves generally parallel and adjacent to the shoreline within the surf zone.

Littoral drift” means material such as sand and stones moved near the shore in the littoral zone under the influence of waves and currents.

Lowest Living Floor means the lowest portion of the lowest horizontal support member of the lowest enclosed space used for living purposes, which includes working, sleeping, eating, cooking, recreation, or combination thereof. A floor used only for storage shall not be considered a living floor.

Maintenance means any work aimed at keeping a structure in an efficient operating and usable condition. Maintenance does not mean expansion or modification of a structure. Maintenance does not mean changing the general form or extent of the structure.

Material Physical Effect” means, including, but not limited to, any alteration to the existing characteristics of the beach or dune that could significantly, increase the danger of erosion, storm damage or flooding and includes the moving, digging, or removal of beach or the erection of any temporary or permanent structure.

Meteorology means the atmosphere and its phenomena especially as relating to weather.

Modernizing” means the act of updating portions of a structure to give a new character or appearance.

Modification” means a partial change in the form of a structure.

[National North] Geodetic American Vertical Datum (NGAVD) means a fixed reference adopted by the U. S. Government as a standard geodetic datum for vertical elevations.

“Parcel of Real Property” means a single lot, the boundaries of which are set forth in a single deed or similar document.

“Person” means any legal entity including individual, firm, association, organization, partnership, business trust, corporation, company, contractor, user, operator, owner, or any State of local governmental agency (except as noted in Section 2.3) or public district or any officer or employee thereof any individual, partnership, corporation, association, institution, cooperative enterprise, municipality, commission, political subdivision or duly established legal entity.

Porch” means a roofed open or screened area adjoining an entrance to a building.

“Primary Dune” means that dune which roughly parallels the shoreline in a more or less continuous fashion and is generally the first and largest dune encountered moving landward from the shoreline.

Private Beach” means any beach which is not a public beach as defined in these regulations.

“Public Beach” means any beach owned in fee simple title by the Federal or State government or any county, city, town or municipality; or any beach for which the State has obtained an easement or agreement for public use.

Regulated Area” means the specific area within the defined beach that the Department is directed to regulate construction to preserve dunes and to reduce property damage. The regulated area shall be from the seaward edge of the beach as defined above to the landward edge of the third buildable lot in from the mean high water line.

Regulation means, unless stated otherwise, means the Regulations Governing Beach Protection and the Use of Beaches, promulgated pursuant to the Beach Preservation Act of 1972 (7 Del.C. Ch. 68) and all amendments thereto.

Repair means the act of restoring a structure to good condition after it has been damaged. Repair does not mean expansion or modification of a structure.

Revetment means a facing of stone, concrete, or similar material built to protect a shore, or shore structure against erosion by wave action or currents.

Roadway means any improved (hot-mix bituminous concrete or Portland cement concrete) public roadway (maintained by any governmental agency for use by the general public) in existence on the effective date of these Regulations.

Sand Fence means a barrier made of posts, wires and boards or synthetic materials including plastic, nylon and polyester intended primarily to trap and collect wind-blown sand, but which may also be used to channel human and vehicular traffic.

Seawall means an upright structure separating land and water areas, primarily designed to prevent erosion and other damage to upland areas due to wave action. A seawall is generally of heavier or more massive construction than a bulkhead.

Secretary means the Secretary of the Department of Natural Resources and Environmental Control.

Shoreline means the line of intersection of a body of water with the land.

Smallest Subset of Lots” means smallest identifiable group of lawfully subdivided, contiguous lots that exist within a subdivision, development or community separated by either roads or subdivision boundaries. If there are no roads or subdivision boundaries separating groups of lots, the smallest set of lots shall be seven lots.

Structure means any building, pipeline, dock, pier, wharf, boat ramp, groin, jetty, seawall, bulkhead, revetment, or any other piece of work artificially built.

Subdivide means the lawful division of any parcel of land into smaller parcels.

Substantial Amount means any amount, the moving, alteration, or removal of which could significantly increase danger of erosion, storm, damage or flooding.

Substantial Change means any alteration in the existing characteristics of the beach, as determined by the Secretary, that could significantly increase the danger of erosion, storm damage or flooding and including the moving, digging, or removal of beach material or the erection of any permanent of semi-permanent structure.

Substantial Damage” means the damage or destruction of any structure by an act of God to the extent that, in the judgment of the Department, 75% or more of the original structure, or if a building, more than 50% of the original foundation pilings, are unsuitable for incorporation into reconstruction of the structure.

Substantially Improved” means any reconstruction, rehabilitation, addition or other improvement to a structure, the total cost of which equals or exceeds 50% of the market value of the structure before the start of construction of the improvement.

Temporary Structure” means any not permanent, non-habitable structure that can be easily removed from the site within a short time frame using minimal equipment and man power. Examples include, but are not limited to, signs, benches, sheds, ramps, steps or walkways.

Update” means a change to an existing structure intended to improve its integrity or value.

2.0 Administrative Principles Permits and Letters of Approval

2.1 Purpose, Application of Current and Earlier Regulations. The primary purpose of these Regulations is to enhance, protect, and preserve public and private beaches of the State through a permit and letter of approval process. These current Regulations shall not apply to any project for which a valid letter of approval, permit, or extension of the same has been issued by the Division prior to the effective date of these Regulations. However, those provisions of the Department's regulations that governed beach protection and the use of beaches that were in effect prior to the effective date of these current Regulations shall apply to the projects, permits and letters of approval that were authorized or issued before the effective date of these Regulations.

2.2 Approval Requirement

2.2.1 No person shall commence or conduct construction for which approval is required under these Regulations (see Section 4.0) unless and until a letter of approval or the proper permit has been issued.

2.2.2 Before any person shall commence construction of any modification or expansion pursuant to the provisions of this Section, said person shall apply for and be issued a letter of approval or a permit from the Division.

2.2.3 The provisions of Section 3.0 of the Regulations have provided for certain exceptions to the general prohibition against construction seaward of the Building Line. However, prior to the commencement of any construction of any structure, or portion thereof, that is included within one or more of the exceptions set forth in said Section 3.0, the owner of the proposed structure or portion thereof shall apply to the Division for a permit pursuant to the provision set forth in subsection 4.5 of the Regulations. The permit application will be processed pursuant to procedures set forth in Section 5.0 of the Regulations.

2.3 Department Exemption

2.3.1 The Department shall be subject to all the rules and requirements of these Regulations, except that in the performance of its erosion control duties pursuant to the authority granted by the Beach Preservation Act of 1972 (Title 7, Del.C. Ch. 68), the Department shall be exempt from the permit requirements of these Regulations. The Department shall, however, still be subject to any substantive standards and guidelines generally applicable to the construction and placement of shore protection structures and facilities.

2.4 Extensions for Letter of Approval or Permit

2.4.1 These Regulations shall not apply to any project for which a valid letter of approval, permit, or extension of same has been issued by the Division, prior to the effective date of these Regulations. After the effective date of these Regulations no extension shall be granted for a letter of approval or permit issued prior to the effective date of these Regulations. Any letter of approval or permit which was issued without specific time limits has become null and void if construction has not been initiated within one year or completed within two years from August 13, 1981 the effective date of these Regulations.

2.4.2 An extension to the time limits of a permit or letter of approval that was issued after the effective date of these Regulations may be granted by the Division. Before any such extension may be granted, the person who was issued the letter of approval or permit shall submit a written request for the extension. The written request must be received by the Division at least fifteen (15) days prior to the expiration date of the letter of approval or permit and shall contain a detailed explanation of why the extension is necessary, and the date when the project will be completed. In determining whether such an extension will be granted the Division may consider the following: (1) whether reasonable progress is being made toward completion of the project; and (2) any changes that may have occurred in state, federal and local laws, regulations, rules, requirements or administrative policy, which are contrary to aspects of the project that had been originally approved by the Division. In lieu of an extension of the time limits in a letter of approval or permit, the Division may require a person to reapply for a letter of approval or a permit if the Division determines that the facts and circumstances relating to a previously approval approved project require a re-evaluation by the Division.

2.4.2.1 An extension to a letter of approval or permit shall not be granted more than three times.

2.5 Construction Setback Lines - Prior Approvals

2.5.1 At those locations where dune reconstruction has been approved by permit prior to the Regulations promulgated and effective date of these Regulations on August 13, 1981 and a construction setback line mutually agreed upon in writing between an owner/developer and the Division to be the landward toe of the reconstructed dune, that agreed upon line shall prevail over the current Building Line for the purposes of initial construction of a structure upon each affected parcel. Any subsequent additions to, or replacements of, the initially approved structure shall be subject to the Building Line as established pursuant to these Regulations and the appropriate sections thereof. Regardless of the developmental status of the parcels affected by this Section, all construction activities shall be subject to the Building Line upon its future re-establishment pursuant to Ssubsection 2.13 of these this Rregulations.

2.6 Maintenance, Repairs, and Emergency Action

2.6.1 Except as otherwise provided in Ssubsections 2.6.2 and 2.6.3, any Person intending to commence any maintenance or repair work on any structure located in part or entirely seaward of the Building Line, shall apply in writing to the Division for a letter of approval or a permit. No person shall commence such maintenance or repair work until after being issued a letter of approval or a permit by the Division. (See also the provisions of Section 3.0 - Prohibited Activities and Section 4.0 - Activities Requiring a Permit or Letter of Approval from the Division).

2.6.2 The provisions of Section 2.6.1 shall not apply where maintenance or repair work on a structure located in part or entirely seaward of the Building Line is undertaken pursuant to the following limitations or causes:

2.6.2.1 Where a building is involved, and the location of the finished maintenance or repair work is at or above the lowest living floor.

2.6.2.2 The maintenance consists solely of non-structural work such as repainting, replacement of shingles or siding or replacement of windows and doors and any cleaning necessary to maintain the structure.

2.6.2.23 The maintenance or repair work is to a structure, and is necessary because of damage being caused to the structure by some means other than wave action, a flood or erosion.

2.6.2.34 In the event of an extreme emergency, or warning thereof, which may involve grave and imminent danger of substantial property loss and/or personal injuries (e.g., an impending coastal storm), a person may perform work on a structure that is related to the protection of persons and said structure. However, before a person can commence any such emergency protection work, the person owning the structure on which such work shall be performed, or any agent thereof, shall contact the Division to request approval to perform the emergency protection work. The Division's approval or disapproval may be given to the owner, or agent thereof, either orally or in writing. After the emergency, or emergency warning period, the Division may require the removal of any emergency protection work performed pursuant to the provisions of this Section.

2.7 Restoration or Reconstruction After Destruction

2.7.1 If a structure located seaward of the Building Line is completely destroyed, no person shall undertake any restoration or reconstruction of the destroyed structure before the Division issues the person a permit or letter of approval pursuant to the procedures set forth in 4.0 of these Regulations.

2.8 Siting Requirements for Construction and Reconstruction of Structures

2.8.1 If a structure is to be either constructed or reconstructed following the complete destruction of the original structure, and such a structure does not have to be located seaward of the Building Line in order to achieve its intended purpose pursuant to Section 3.01 (a)(4) of these Regulations, then such a structure shall be required to be located entirely landward of the Building Line. However, if the Division determines that there is inadequate space available entirely landward of the Building Line for the construction or reconstruction of a completely destroyed structure, said constructed or reconstructed structure shall be physically located as far landward as possible on the parcel of real property in question, taking into consideration all Federal, State and local laws, rules, regulations, and zoning and building ordinances.

2.97 Other Requirements and Approvals

2.97.1 A person who is issued a permit or letter of approval by the Division pursuant to these Regulations is not exempted from obtaining any other permit or approval required by Federal, State or local laws, rules, regulations, and building and zoning ordinances.

2.108 General Permit Considerations

2.108.1 The Division, in considering applications, shall take into account the geology, geomorphology, meteorology and hydraulics of the area.

2.119 Sole Jurisdiction

2.119.1 All structures, devices and facilities for the enhancement, preservation or protection of beaches shall be under the sole jurisdiction of the Department. None of these shall be changed in any way except as provided in these Regulations.

2.120 Building Line Format

2.120.1 The Building Line shall be shown on topographic maps at a scale of one (1) inch equals fifty (50) feet for all shoreline areas of Delaware Bay and the Atlantic Ocean Coast from, and including, Pickering Beach to the Delaware-Maryland line at Fenwick Island, where privately owned structures, either existing or potential, may be affected by the establishment of the Building Line. The Building Line shall be shown as a series of straight lines connected together at points whose locations are identified by reference to the Delaware State Plane Coordinate System. No point shall be located more than 500 feet from an adjoining point.

2.131 Building Line Re-establishedment

2.131.1 When, in the opinion of the Secretary, storms or other natural phenomena cause a substantial permanent long term change in the seaward contour used to establish the Building Line, the Division may, following public hearing, re-establish the Building Line in its entirety or for the portions of the coast where the natural phenomena have caused substantial long term changes from information provided by topographic survey.

2.142 Re-establishment Effects on Lot Status

2.142.1 Re-establishment of the Building Line may place parcels of land, lawfully subdivided after the effective date of these Regulations, in a position of having insufficient space to construct a structure landward of the newly established Building Line. These parcels shall be subject to the appropriate permit requirements of Section 4.0 of this regulation.

2.153 Savings Clause

2.153.1 If any provision of these Regulations, or the application of such provision to any person or circumstances, is held invalid, the remainder of these Regulations, and the application of such provision to persons or circumstances other than those to which it shall have been held invalid, shall not be affected.

3.0 Prohibited Activities

3.1 Construction Seaward of the Building Line

3.1.1 No person shall commence the construction of any structure, or portion thereof, seaward of the Building Line on any parcel of real property, except where one or more of the following conditions exist:

3.1.1.1 The Division has made a determination during the permit application processing stage that the size of the area of the parcel of real property located landward of the Building Line is inadequate for construction of the proposed structure or a portion thereof. However, the Division's determination as to the adequacy of the area of the parcel of land located landward of the Building Line, or as to any modification or redesign shall not conflict with any Federal, County or local laws, regulations, or planning, zoning and building ordinances.

3.1.1.2 That the dimensions and location of the structure, or portions thereof, as proposed and other design aspects of the proposed construction project, including, but not limited to, parking lots and landscaping, cannot be modified or redesigned in order to have the final structure or portion thereof located either less seaward or completely landward of the Building Line in accordance with the four-step process outlined in subsections 3.1.1.2.1 through 3.1.1.2.4 of this regulation. (See 5.0 Section subsection 5.3.2 of this regulation for further explanation of what the Division will examine when a permit application is processed and whether or not the proposed structure, or portion thereof, may have to be modified or redesigned). However, the Division's determination as to the adequacy of the area of the parcel of land located landward of the Building Line, or as to any modification or redesign shall not conflict with any Federal, County or local laws, regulations or planning, zoning and building ordinances. (Note that this exception shall not apply if the provisions of subsection 3.1.1 of this regulation are applicable to the parcel of land in issue.) A person is not required to follow the requirements of the four-step process if they demonstrated through the submission of a sealed survey of the lot that all construction will be located entirely landward of the Building Line. In this case, the applicant must apply for a letter of approval as required by subsection 4.8 of this regulation.

3.1.1.2.1 All construction must begin at the setback line established for the landward property boundary by the county or local municipality in which the property is located. Porches, decks and entrance ways are not permitted along this wall of the building, except those which are recessed into the exterior wall of the structure or alongside the structure. Steps may extend into the setbacks as long as permissible by county and local regulations, and;

3.1.1.2.2 The structure must occupy all of the area available between the side yard setbacks, and;

3.1.1.2.3 The square footage of the footprint of the structure (living area only, not including porches or decks) shall not exceed the average square footage that exists among adjacent structures within the smallest subsets of lots, and;

3.1.1.2.4 Seaward penetration over the Building Line shall not exceed the average encroachment that exists among adjacent structures within the smallest subset of lots. Any decks constructed along with the structure must meet the requirements of subsection 3.1.1.3 of this regulation.

3.1.1.3 Whenever a deck or porch is being constructed along with a new building, and said deck or porch is located at or above the lowest living floor of the building, said deck or porch is also making use of the foundation of said building (i.e. cantilevering) and said deck or porch shall not extend beyond the most seaward point that is the average distance seaward of the Building Line of any lawfully constructed building, or deck or porch of a similar nature that is already existing on any immediately adjacent parcels of real property located within the smallest subset of lots, within the same subdivision as the parcel of real property on which the building, or deck or porch is proposed. Future enclosure of the cantilevered deck or porch is prohibited and the area underneath the deck shall remain open and free of all obstructions.

3.1.1.4 The Division has made a written determination that the proposed structure, or a portion thereof, must be located seaward of the Building Line on a parcel of land in order that the intended purpose of the structure, or a portion thereof, will be achieved. The provisions of this Section and subsection may apply to the following types of structures: pipelines, docks, piers, wharves, boat ramps, and other harbor structures, as well as other types of structures that have the purpose of protecting the beach or shore, preventing beach erosion, and carrying out the purposes of the Act and the Regulations. However, for purposes of this Section and subsections, a building, patio, deck, swimming pool, carport, driveway or similar type of structure shall not be considered by the Division as being the type of structure that must be located seaward of the Building Line on a parcel of land in order to achieve the intended purpose of the structure. The Division may require that these latter types of structures, or portions thereof, be constructed landward of the Building Line, or not constructed at all.

3.1.1.5 If a structure is completely removed from its foundation for replacement of said foundation, and 75% or more of the original structure remains intact, and such a structure does not have to be located seaward of the Building Line in order to achieve its intended purpose pursuant to subsection 3.1.1.4 of this regulation, then such a structure shall be required to be located entirely landward of the Building Line or shall be located as far landward as possible on the parcel of real property in question, taking into consideration all Federal, State and local laws, rules, regulations and zoning and building ordinance. Under these circumstances subsection 3.1.1.2 of this regulation (the 4-step process) would not apply.

3.1.1.6 In those cases where the mapped Building Line either transects or is landward of lots that, in turn, are landward of lots with existing habitable structures, the Building Line will not be used to modify either location or dimension of buildings on the more landward lot.

3.1.2 Except as provided in subsections 3.1.1.3 and 3.1.1.4 of these Regulations, no person shall construct any structure, or portion thereof, on any parcel of real property, or portion thereof, that is located seaward of the Building Line whenever the following facts and circumstances exist:

3.1.2.1 The parcel of real property, or a portion thereof, on which a proposed structure, or portion thereof, would be constructed, was subdivided from a large parcel of real property after August 13, 1981. In addition, at the time said parcel of real property, or portion thereof, was subdivided from a larger parcel of real property, construction of a structure, or portion thereof, would not have been approved by the Division because the size of the area landward of the Building Line on the smaller subdivided parcel of real property was inadequate. (See Section 2.14 subsection 2.12 and Section 4.0 of the Regulations.)

3.1.3 The provisions of 3.0 of the Regulations have provided for certain exceptions to the general prohibition against construction seaward of the Building Line. However, prior to the commencement of any construction of any structure, or portion thereof, that is included within one or more of the exceptions set forth in said 3.0, the owner of the proposed structure or portion thereof shall apply to the Division for a permit pursuant to the provision set forth in Section 4.5 of the Regulations. The permit application will be processed pursuant to procedures set forth in 5.0 of the Regulations.

3.2 Modification or Expansion of Structures Seaward of the Building Line

3.2.1 Before any person shall commence construction of any modification or expansion pursuant to the provisions of this Section, said person shall apply for and be issued a letter of approval or a permit from the Division.

3.2.2 A person is prohibited from modifying or expanding any structure, or portion thereof, seaward of the Building Line, including those structures, or portions thereof, that were (1) constructed prior to the effective date of these Regulations, or (2) were constructed pursuant to the provisions of Ssubsection 2.4 of these this Regulations, unless one or more of the following exceptions apply to the proposed modification or expansion at issue:

3.2.21.1 The provisions of subsection 3.1.1.4 of the Regulations should be applied to the proposed modification or expansion because the intended purpose of the structure, or portion thereof, that is to be modified or expanded must be achieved. A permit shall be required for work under this Section. See Section 4.0 of these Regulations.

3.2.21.2 The modification or expansion consists of only a deck or porch located at or above the lowest living floor of a building, and the modification or expansion makes use of the foundation of said building (i.e. cantilevering) that existed prior to said modification or expansion. However, any deck or porch or portion thereof, that is modified or expanded pursuant to any provision of this Section shall not extend beyond the most average distance seaward point of the Building Line of any existing lawfully constructed buildings or decks or porches of a similar nature that is already existing on any immediately adjacent parcels of real property that is are located within the smallest subset of lots, within the same subdivision as the parcel of real property on which the modification or expansion is proposed. A letter of approval shall be required for work under this the Section. See Section 4.0 of these Regulations.

3.3 Restoration or Reconstruction of Structures Seaward of the Building Line

3.3.1 If a structure located seaward of the Building Line is substantially damaged, no person shall undertake any restoration or reconstruction of the damaged structure before the Division issues the person a permit or letter of approval pursuant to the procedures set forth in Section 4.0 of this regulation.

3.4 Siting Requirements for Construction and Reconstruction of Structures

3.4.1 If a structure is to be either repaired or reconstructed following substantial damage or is to be substantially improved, and such a structure does not have to be located seaward of the Building Line in order to achieve its intended purpose pursuant to subsection 3.1.1.4 of this regulation, then such a structure shall be required to be located entirely landward of the Building Line. However, if the Division determines that there is inadequate space available entirely landward of the Building Line for the repair or reconstruction of a substantially damaged or substantially improved structure, said repaired or reconstructed structure shall be physically located as far landward as possible on the parcel of real property in question, taking in to consideration all Federal, State and local laws, rules, regulations and zoning and building ordinance. (See subsection 3.1.1 of this regulation.)

3.5 Footprint Requirement:

3.5.1 No property owner shall be prevented within the regulated area from repairing, modifying, modernizing, updating, or improving their existing structure, or by performing such actions, be required to relocate or reduce in size so long as these repairs, modifications, or improvements are within the existing structure’s footprint.

3.6 Effect of Beach Nourishment

3.6.1 When considering the reconstruction of buildings on lots fronting the Ocean or Delaware Bay that are either partially or completely seaward of the Building Line that have sustained substantial damage through acts of God or other accidental events, the Division will consider the effect of beach nourishment work that has enhanced the beach and dune in such areas. Furthermore, in any such case, where Federal or State agencies have constructed and continue to maintain a beach and dune that conforms to coastal engineering standards of storm protection (as defined in these regulations) property owners shall be permitted to rebuild a structure, in a location which has this level of protection, in the same footprint.

3.37 Other Prohibited Activities

3.37.1 The following activities are prohibited:

3.37.1.1 The operation of any motorized vehicle or machine on, over or across the primary dune on any State-owned or maintained beach except at those locations specified by the Department for such use (see current State Parks Rules and Regulations for additional rules);

3.7.1.2 Transportation or storage of any type of boat across or on the primary dune on any State-owned or maintained beach except at locations approved or permitted by the Department;

3.37.1.23 Pedestrian traffic on, over or across the primary dune on any State-owned or maintained beach except at those locations specified by the Department for such use;

3.37.1.34 The alteration, moving or removal of any facility, improvement or structure installed or maintained by the Department for enhancement, preservation or protection of any beach; and

3.37.1.45 The damaging, destruction or removal of any trees, shrubbery, beach grass or other vegetation growing on any State-owned or maintained beach seaward of the Building Line.

3.8 Temporary Structures:

3.8.1 The placement of seasonal or otherwise temporary structures seaward of the Building Line and seaward of the dune on the dry beach may be allowed for a period of up to a year or such lesser period as specified with a Letter of Approval from the Department. It must be demonstrated by the applicant that the design and deployment of the temporary structure can be done so that the structure can be easily removed or otherwise relocated landward of the Building Line in a short time frame. Temporary structures must be removed from the site during the time frame established in the letter of approval and in the case of the threat of a coastal storm.

3.8.1.1 If the temporary structures, such as, but not limited to, tents, wedding alters, chairs or tables, are being placed on the beach for an event that will last only 72 hours or less, the requirement to obtain a letter of approval is waived. However, the provisions of subsection 3.7.1.5 of this regulation still apply.

4.0 Activities Requiring a Permit or Letter of Approval from the Division

4.1 General Rule

4.1.1 No permit shall be issued for any activity prohibited by any provision of the Regulations. Procedures for processing applications are set forth in Section 5.0 of the Regulations.

4.2 Permit Application; Fee

4.2.1 Any person applying for a permit pursuant to the provisions of Section 4.0 of the Regulations must apply to the Division on an application form provided by the Division. Any person submitting a permit application form to the Division pursuant to the provisions of Section 4.0 of the Regulations shall at the same time submit an application fee of $150.00 for each permit application.

4.3 Construction of Beach Erosion Control or Shore Protection Structures or Facilities Seaward of the Building Line

4.3.1 No person shall commence or conduct, without a permit therefor from the Division, construction of any structure or facility on any beach seaward of the Building Line, the primary function of which is beach erosion control or shore protection including, but not limited to, groins, jetties, seawalls, revetments, dikes, bulkheads, and beach nourishment; except that ordinary dune maintenance, as determined by the Division, including the proper installation of sand fence and the planting and fertilization of stabilizing vegetation, shall not require a permit.

4.4 Construction of Pipelines or Harbor Works Seaward of the Building Line

4.4.1 No person shall commence or conduct without a permit therefor from the Division, construction seaward of the Building Line, or any pipeline, dock, pier, wharf, ramp or other harbor work.

4.5 Construction of a Structure Seaward of the Building Line; Permits; Exception for Beach Access Structures

4.5.1 Except as provided pursuant to the provisions of Ssubsections 4.3, 4.4, or 4.5.3 of the Regulations, before any person commences the construction of any structure, or portion thereof, that would be located seaward of the Building Line, said person must have been issued a permit for the construction by the Division.

4.5.2 Before any permit is issued by the Division pursuant to Ssubsection 4.5.1 of the Regulations for the construction of any structure, or portion thereof, seaward of the Building Line, the person applying for the permit must provide the Division with written documentation that the proposed structure, or portion thereof, will be constructed in accordance with Division requirements relating to location and design criteria, which are intended to prevent or minimize any damage to the beach, and also all the provisions of the Act and the Regulations.

4.5.3 A person is not required to follow the requirements of Ssubsection 4.5.1 or 4.5.2 of the Regulations if a person intends to construct a structure, or portion thereof, that is going to be used only for the purpose of providing pedestrian access to and from the berm and foreshore across the dune zone. However, before any person commences the construction for such a beach access structure, or any portion thereof, that would be located seaward of the Building Line, said person must have been issued a letter of approval for the construction by the Division. A person may receive said letter of approval after applying to the Division on an application form that shall be made available by the Division. The Division shall process said application form pursuant to the procedures set forth in the provisions of Ssubsection 4.8 of the Regulations.

4.5.3.1 For the purposes of best protection of the dunes, and to meet the needs of larger beach communities, pedestrian dune crossovers may be constructed to certain widths. The total number of residences that are served by each crossover will be determined by the Division by dividing the number of possible single family dwellings within a subdivision on non-ocean front or bay front lots by the number of community pedestrian dune crossovers within that subdivision.

4.5.3.1.1 Crossovers serving one or two single family residences shall not be wider than four feet

4.5.3.1.2 Community crossovers that serve anywhere between three to nine single family residences shall not be wider than five feet.

4.5.3.1.3 Community crossovers that serve 10 or more single family residences shall not be wider than six feet.

4.5.3.1.4 Crossovers serving persons with special needs will be evaluated on a case by case basis.

4.6 Other Activities Seaward of the Building Line

4.6.1 No person shall commence or conduct any of the following activities on any beach without a permit therefor from the Division: the alteration, digging, mining, moving, removal or deposition of any substantial amount of beach or other materials, or the significant removal of vegetation on any beach seaward of the Building Line which may affect enhancement, preservation or protection of beaches.

4.7 Mitigating Measures

4.7.1 In rendering its decision on requests for permits and letters of approval pursuant to these Regulations, the Division shall make a determination regarding the potential adverse effects of the proposed structure or activity. If, in the opinion of the Division the potential for damage to the beach seaward of the Building Line is increased as a result of the proposed structure or activity, the Division may require the applicant to take mitigating measures (including, but not limited to beach nourishment, dune construction, and/or dune maintenance) to reduce such damage potential. When the Division requires such mitigating measures, the applicant, his their successors, heirs and assigns, shall be required to maintain these measures for the life of the structure or activity. Failure to comply with the mitigating measures prescribed by the Division shall be cause for removal of the structure or termination of the activity and restoration of the beach, as nearly as possible, to its original condition at the expense of those persons owning the structure or conducting the activity, or for the Division to take the necessary actions to bring the owner into compliance and to place a lien on such property for all reasonable costs and expenses incurred by the Division, whichever action the Division deems most appropriate.

4.8 Construction Activities Landward of the Building Line and Within the Beach Regulated Area

4.8.1 No person shall commence or conduct construction of any structure or the alteration, digging, mining, moving, removal or disposition of any substantial amount of beach or other materials landward of the Building Line and within the beach area without a letter of approval from the Division. To obtain the written approval, the applicant shall furnish to the Division a completed application on forms available from the Division.

4.8.2 Upon receipt of an application for approval, the Division shall consider the effect of the proposed project on beach enhancement, preservation and protection. The Division may undertake any investigation or activity it deems necessary to carry out the purposes of this Act. If the Division determines such a project may have a substantial effect on beach enhancement, preservation and protection, the applicant shall be directed to follow the procedures for obtaining a permit applicable under Section 4.0 of the Regulations. The Division shall make a decision on the application that may include terms and conditions which it determines will best implement the purposes of the Act and these Regulations. The Division shall give written notice with reasons for the decision to the applicant.

5.0 Procedures for Processing Permit Applications

5.1 The Division

5.1.1 Applications shall be considered and permits issued or denied by the Division in accordance with the purposes and intent of the Act and these Regulations.

5.2 Notice

5.2.1 Upon receipt of a permit application in proper form, the Division shall advertise in a daily newspaper of state-wide circulation and in a newspaper of general circulation in the county in which the activity is proposed:

5.2.1.1 That the application has been received;

5.2.1.2 A brief description of the nature of the application; and

5.2.1.3 That comments will be received for 15 calendar days by the Division regarding the application.

5.2.2 The Division shall also mail notice of the above to all adjacent property-owners as listed in the permit application, and make the application available for public inspection at the Dover office of the Division. A decision shall not be rendered on any permit application until at least 20 calendar days after notice has been published and mailed to adjacent property owners, and the application has been made available for public inspection, in accordance with this Section.

5.3 Specific Information to be Examined by the Division; Investigatory Authority of the Division and Its Agents; Authority of Division to Require Special Conditions or Modifications

5.3.1 In addition to the general categories of information that are provided for pursuant to Section 2.10 subsection 2.8 of the Regulations whenever the Division is deciding to issue a Permit pursuant to the Regulations, the Division shall take into consideration any relevant information relating to the following:

5.3.1.1 Any comments received by the Division;

5.3.1.2 The effect of the proposed construction on shoreline recession, beach erosion, flooding, and potential damage to the parcel of real property that is the subject of the permit application, and potential damage to any other parcel of real property, public lands, or personal property;

5.3.1.3 The feasibility of alternative protection from storm damage that may be available;

5.3.1.4 The historical average rate of shoreline change for the general area nearby and including the parcel of real property that is the subject of the permit application;

5.3.1.5 The design modifications which may mitigate the impact of the proposed construction on the part of the beach that is located seaward of the Building Line (see Ssubsection 5.3.2 (b) below for further information); and

5.3.1.6 Any other factors or information that the Division determines to be relevant to the subject matter of the permit and carrying out the purposes and intent of the Regulations and the Act.

5.3.2 In determining if the Division shall require that the dimensions or location of a proposed structure, or portion thereof, or other design aspects are to be modified or redesigned pursuant to the provisions of Ssubsection 3.1.1.2 of the Regulations, the Division, in addition to what is required in Sections 2.10 subsections 2.8 and 5.3.1, shall balance the actual and potential hardships or benefits that may be experienced by the person owning the structure or portion thereof against the actual and potential hardships or benefits that the State, the public and adjacent landowners may experience. The Division while carrying out the balancing test may take into consideration the following factors:

5.3.2.1 The purposes and provisions of the Act and the Regulations;

5.3.2.2 The likelihood and amount of actual, or potential for, expenditures of federal and state revenues for maintaining, repairing or restoring the parcel of real property prior to construction, after construction and after any natural disaster (e.g. storm);

5.3.2.3 The protection of the State, the public and any adjacent landowners from actual and potential financial and property loss;

5.3.2.4 The actual and potential financial or personal losses to the owner of the structure or portion thereof;

5.3.2.5 The feasibility of any modification or redesign required by the Division, keep in mind any increased or decreased costs, in achieving the purpose and function of the structure or portion thereof as originally planned;

5.3.2.6 Any design alternatives or amendments to the original designs submitted to the Division by the owner of the proposed structure or portion thereof; and

5.3.2.7 Any other factor the Division determines to be relevant.

5.3.3 The Division or Department, and any agents thereof, may do any of the following acts while attempting to carry out the purposes and intent of the Regulations and the Act, or while processing an application for a permit or request for a letter of approval:

5.3.3.1 Make on-site inspections of any type of structure, or portion thereof, or any real property regulated by the provisions of the Regulations or the Act.

5.3.3.2 Communicate with any party to discuss any matter relating to the Regulations or the Act.

5.3.3.3 Undertake formal or informal investigations or activities as are necessary to carry out the propose and intent of the Regulations and the Act.

5.3.4 In addition to the provisions of Ssubsection 4.7 of the this Regulations, the Division may establish special permit conditions, and/or require modification of any proposed structure or activity in order to (1) prevent increased erosion damage to the parcel of real property in issue, nearby parcels or real property, or public lands, and/or (2) reduce public expenditures for beach protection.

5.4 Decision

5.4.1 The Division shall make a decision on the application which it determines will best implement the purposes of the Act and these Regulations. The Division shall give written notice with reasons to the applicant, to adjacent property owners as listed in the permit application and to other persons who have requested that they be notified of the decision on that application.

6.0 Appeal From the Division's Decision

6.1 Activity Pending Appeal

6.1.1 The applicant shall not commence any activity regulated under Section 4.0 of the Regulations until such time as a final determination has been rendered on the matter and the appeal period has expired without an appeal having been taken, or, if appealed, the appeal process has been exhausted.

6.2 Procedures

6.2.1 Any person or persons, jointly or severally, or any taxpayer, or any officer, department, board or bureau of the state, aggrieved by any decision of the Division, many appeal to the Secretary by giving written notice of appeal to the Secretary, and to the applicant if other than the appellant. Such notice shall be by certified or registered mail within twenty (20) calendar days of the Division's decision, and shall specify: (1) the interest of the appellant; (2) the basis of the appeal; and (3) the specific law(s), regulation(s) or other legal authority(ies) alleged to have been violated by the Division's decision. A public hearing may be held on any such appeal, upon request, whenever the Secretary deems the hearing request meritorious. A request for a public hearing shall be deemed meritorious when the appeal is not frivolous and the notice of appeal exhibits a reasonable familiarity with the Division's decision. The public hearing shall be conducted as follows:

6.2.1.1 For any hearing on an application, notification shall be served upon the applicant as summonses are served or by registered or certified mail not less than twenty (20) calendar days before the time of said hearing. Notice shall also be published in a newspaper of general circulation in the county in which the activity is proposed and in a daily newspaper of general circulation throughout the State not less than twenty (20) calendar days before the time of said hearing.

6.2.1.2 The appellant may appear personally or be represented by counsel at the hearing and produce any competent evidence in his their behalf. The Secretary or his the Secretary’s authorized designee may administer oaths, examine witnesses, and issue, in the name of the Department, notices of hearings or subpoenas requiring the testimony of witnesses and production of books, records or other documents relevant to any matter involved in such hearing.

6.2.1.3 A verbatim transcript of testimony at the hearing shall be prepared and shall, along with the exhibits and other documents introduced by the Secretary or other parties, constitute the record. The Secretary or his the Secretary’s authorized designee shall make findings of fact based on the record. The Secretary shall then enter an order that will best further the purposes of the Act and these Regulations, and the order shall include reasons. The Secretary shall promptly give written notice of the order to parties who participated in the hearing.

7.0 Appeal From the Secretary's Decision

7.1 Appeal Procedure

7.1.1 Any person or persons, jointly or severally, or any taxpayer, or other officer, department, board or bureau of the State, aggrieved by a final order of the Secretary may, within thirty (30) calendar days, appeal to the Superior Court as provided in 7 Del.C. §6803(g).

8.0 Cease and Desist Orders, Violations and Penalties

8.1 Cease and Desist Orders

8.1.1 The Secretary shall have the power to issue a cease and desist order to any person who violates any provision of the Act or Regulations. Any such cease and desist order shall expire (1) after thirty (30) days from the date of its issuance, or (2) upon withdrawal of said order by the Secretary, or (3) when the order is superseded by an injunction, whichever occurs first.

8.2 Violations and Penalties

8.2.1 Any person who violates any provision of the Act, or Regulations, or violates a cease and desist order of the Secretary, shall be fined not less than $100 nor more than $5,000 or imprisoned for not more than two (2) years, or both, and, in addition, shall reimburse the Department for its reasonable expenditures in remedying damage created. Whoever, without authority from the Department, alters, moves or carries away any substantial amount of beach material (including, but not limited to, sand or pebbles), or alters, damages or destroys any groin, jetty, bank, dike, dune, bulkhead, seawall, breakwater or any other facility, improvement or structure installed or maintained by the Department for the enhancement, preservation or protection of the beach, shall be liable for a civil penalty imposed by the Court of Common Pleas of not less than $200 nor more than $5,000 for each completed violation. If the violation has been completed and there is a substantial likelihood that it will recur or if it is a continuing violation, the Department may also seek a permanent or preliminary injunction or temporary restraining order in the Court of Chancery.

8.2.2 Any coastal structure erected, or excavation created, in violation of these regulations is hereby declared to be a public nuisance, and such structure shall be forthwith removed or such excavation refilled after written notice by the Department directing such removal or filling. In the event the structure is not removed or the excavation refilled as directed within a reasonable time, the Department may remove such structure or fill such excavation at its own expense. The person who erected the structure or created the excavation declared to be a public nuisance shall be liable for all expenses incurred by the Department in removing the structure or filling the excavation. The Secretary shall submit a detailed billing for the costs involved in abating the public nuisance to the person responsible. In the event that said billing is not paid by the person responsible within 30 days, the Department may file suit in the appropriate court seeking to compel payment.

8.2.3 Any person who:

8.2.3.1 Violates any condition or limitation in a permit issued pursuant to this chapter;

8.2.3.2 Engages in any activity prohibited by this chapter; or

8.2.3.3 Violates any regulation duly promulgated according to this chapter,

Shall upon conviction be fined not less than $200 nor more than $5,000, or imprisoned for not more than 2 years, or both, and in addition shall reimburse the Department for its reasonable expenditures in remedying damage created.

8.2.4 For the purposes of subsection © of this Section, each and every day that a permit condition or limitation is violated, an activity engaged in which is prohibited by this chapter or a regulation violated is deemed a separate offense.

8.2.5 Any expenses or civil penalties collected by the Department under this Section are hereby appropriated to the Department to carry out the purposes of this chapter.

8.3 Jurisdiction

8.3.1 Justices of the Peace shall have original jurisdiction to hear and determine violations under this Section.

9.0 Procedures for Adoption of Changes to the Regulations

9.1 Hearing

9.1.1 The Secretary, or his the Secretary’s authorized designee, shall hold a public hearing on any changes to the Regulations that he shall propose for adoption. For a hearing on the proposed changes to the Regulations, notification shall be published in a newspaper of general circulation in each county of the State and in a daily newspaper of general circulation throughout the State. Such notification shall include (1) a brief description of the proposed changes to the Regulations, (2) the time and place of the hearing, and (3) the time and place where copies of the proposed changes may be examined and/or obtained. Such notice shall also be sent to any person who has requested notification from the Department by providing their name and mailing address.

9.2 Decision

9.2.1 Following the public hearing, the Secretary may adopt, with or without modifications, the proposed changes to the Regulations. This adoption shall be a final order for purposes of Section 7.0 of the Regulations.

10 DE Reg. 870 (11/01/06)
20 DE Reg. 120 (08/01/16) (Final)
 
+